This post has few formulae used in the project management. These are useful to get the real-time problems solved quickly.
Planned Value (PV) = Planned % complete * budget at completion(EIAC).
PERT formula is Estimate = (Optimistic +(Most Likely*4)+Pessimistic)/6
The formula for the number of channels is n*(n-1)/2, where n is is the number of stakeholders.