11. You are a project manager for a major golf club manufacturer. Your team is working on developing a new line of golf clubs for the upcoming season. It was planned that you will meet with the stakeholders after the first few production sets were ready and allow them to try the clubs. You are reviewing how effective this type of stakeholder meeting is. Why would this type of meeting take place?
A. To aid in performance testing of the product
B. To further engage stakeholders in the project
C. To smooth out any issues that may exist with stakeholders
D. To allow the stakeholders to audit the product
Answer: C, The Control Stakeholder Engagement process monitors stakeholder relationships.
12. You are a project manager overseeing the development of a new console video game and are currently involved in the Monitor and Control Project work process. A working beta of the game is supposed to be available in the next two weeks to demo at an investor's conference. However, it is behind schedule due to problems that occurred when adding bonus content. Which option is the BEST course of action?
A. Continue as scheduled and demo the product that is available
B. Obtain the latest performance reports to verify the status of development
C. Issue a change request to minimize the scope for the release
D. Initiate a change request to have extra resources removed from the project
Answer: C, You should analyze the situation with the project management team and determine a solution. By doing this, you and the team will realize that it was only after the bonus content was added that the project began to have issues. For the conference, you may determine it would be in the best interest to disable the features that are causing problems, thus minimizing the scope. This way the investors can see a working beta, but not be distracted by fancy features that may or may not work. To do this, a change request would need to be issued to disable the features causing the problems.
13. You are managing a project that is overseeing the expansion of a local car dealership that specializes in performance vehicles. The project has been scheduled to take 16 weeks. The total cost of the project is set at $500,000. At the seven week mark of the project, it has been determined that the project is one week behind schedule, and the cost so far is $250,000. At this point, which option represents the planned value of the project?
A. $218,750
B. $62,500
C. $31,250
D. $187,500
Answer: A, Solution can be calculated with the formula Planned Value (PV) = Planned % complete * budget at completion(EIAC).
By dividing the current point in the schedule, which is week seven, by the total number of weeks in the project, which is 16 weeks, we can calculate planned % complete. The result is 7/16 = 0.4375 or 43.75%. By multiplying this value with the EIAC we get the PV = 0.4375 * $500,000, which is $218,750.
14. You are currently involved in controlling procurements on a mission critical project for your organization. A seller has been contracted to provide a high load winch system. The winch that was to be supplied was rated at 1,000 pounds, but it is currently unavailable and will be replaced with the 1,200 pound model. This will result in a change to the contract. Who would be eligible to make a change of the contract?
A. The project management office
B. The function manager of the contracting company
C. The CEO of the contracted company
D. The procurement office
Answer: D, As contracts are formal and legally binding documents that use specialized and technical language, only qualified individuals should prepare them. These qualified individuals include the contracting officer, procurement office, and legal counsel. A project manager would not be considered a contracting officer.
15. You are managing a construction project that is creating a new set for a talk show. The show is set to premiere next month. The backdrop is nearing completion. However, the main stage is only 50% complete. You move a few of the human resources to the main stage team. Which technique did you use?
A. Scheduling tool
B. Adjusting leads and lags
C. Resource levelling
D. Schedule compression
Answer: C, Resource leveling is a technique that is used to allot the proper amount of resources to a specific task. Since one task is nearing completion, and another task is only half done, resources could be moved from the task that all tasks can be more aligned with the schedule.
16. You are the project manager on an IT project that is performing decision analysis and resolution to identify the best possible solution. There is a 10% chance that a component you are going to upgrade will be difficult to integrate and cost $3,000 in rework and delays. There is also a 50% chance that the component will save $5,000 in time and effort that would have been used to build the component from scratch. What is the expected monetary value for these two possibilities?
A. $3,300
B. $7,500
C. $2,200
D. $8,000
Answer: C, The expected monetary value(or EMV) of the problems integrating the component is the probability(10%) times the cost ($3,000), but do not forget that since it is a risk, that number should be negative. So it's EMV is 10% * $3,000 = -$300. The savings from not having to build the component from scratch is an opportunity. It has an EMV of 50% * $5,000 = $2,500. By adding them up we get -$300 + $2,500 = $2,200.
17. Schedule is represented in different ways. You are a project manager on a construction project and want to view the scheduled activities in such a way that it is easy to view the start and end dates of each activity. Which tool is the best fit for this scenario?
A. PERT chart
B. GANTT chart
C. Precedence diagram
D. Network diagram
Answer: B, GANTT chart shows activity start and end dates as well as expected durations but do not usually show dependencies. This is also called as Bar charts.
18. What is the critical path of the project? Refer to the network diagram provided in the image above.
A. ABEGH
B. ABDFH
C. ACGH
D. ABEFH
Answer: A, Critical path is the list of activities that have zero total float.
19. Which executing processes can result in change results?
A. Conduct procurements, Acquire Project Team and Manage Stakeholder Engagement
B. Manage Communications, Manage Project Team and Perform Quality Assurance
C. Perform Quality Assurance, Direct and Manage Project Work and Develop Project Team
D. Direct and Manage Project Work, Conduct Procurements and Manage Stakeholder Engagement
Answer: D, Change requests can result from the following executing processes.
- Direct and Manage Project Work
- Conduct Procurements
- Manage Stakeholder Engagement
20. Which option describes the MAIN purpose for creating a management reserve?
A. Create a reserve for unidentified risks when the project that will occur
B. Create a reserve for unidentified risks when the project that may or may not occurs
C. Create a reserve for identified risks when the project that will occur
D. Create a reserve for identified risks when the project that may or may not occurs
Answer: B, A management reserve is used to create a reserve for unidentified events that may or may not occur during the project. Management can use their experience to determine the prudence to provide a reserve for unknown events that are uncertain to occur. This type of event is sometimes described as an unknown.
A. To aid in performance testing of the product
B. To further engage stakeholders in the project
C. To smooth out any issues that may exist with stakeholders
D. To allow the stakeholders to audit the product
Answer: C, The Control Stakeholder Engagement process monitors stakeholder relationships.
12. You are a project manager overseeing the development of a new console video game and are currently involved in the Monitor and Control Project work process. A working beta of the game is supposed to be available in the next two weeks to demo at an investor's conference. However, it is behind schedule due to problems that occurred when adding bonus content. Which option is the BEST course of action?
A. Continue as scheduled and demo the product that is available
B. Obtain the latest performance reports to verify the status of development
C. Issue a change request to minimize the scope for the release
D. Initiate a change request to have extra resources removed from the project
Answer: C, You should analyze the situation with the project management team and determine a solution. By doing this, you and the team will realize that it was only after the bonus content was added that the project began to have issues. For the conference, you may determine it would be in the best interest to disable the features that are causing problems, thus minimizing the scope. This way the investors can see a working beta, but not be distracted by fancy features that may or may not work. To do this, a change request would need to be issued to disable the features causing the problems.
13. You are managing a project that is overseeing the expansion of a local car dealership that specializes in performance vehicles. The project has been scheduled to take 16 weeks. The total cost of the project is set at $500,000. At the seven week mark of the project, it has been determined that the project is one week behind schedule, and the cost so far is $250,000. At this point, which option represents the planned value of the project?
A. $218,750
B. $62,500
C. $31,250
D. $187,500
Answer: A, Solution can be calculated with the formula Planned Value (PV) = Planned % complete * budget at completion(EIAC).
By dividing the current point in the schedule, which is week seven, by the total number of weeks in the project, which is 16 weeks, we can calculate planned % complete. The result is 7/16 = 0.4375 or 43.75%. By multiplying this value with the EIAC we get the PV = 0.4375 * $500,000, which is $218,750.
14. You are currently involved in controlling procurements on a mission critical project for your organization. A seller has been contracted to provide a high load winch system. The winch that was to be supplied was rated at 1,000 pounds, but it is currently unavailable and will be replaced with the 1,200 pound model. This will result in a change to the contract. Who would be eligible to make a change of the contract?
A. The project management office
B. The function manager of the contracting company
C. The CEO of the contracted company
D. The procurement office
Answer: D, As contracts are formal and legally binding documents that use specialized and technical language, only qualified individuals should prepare them. These qualified individuals include the contracting officer, procurement office, and legal counsel. A project manager would not be considered a contracting officer.
15. You are managing a construction project that is creating a new set for a talk show. The show is set to premiere next month. The backdrop is nearing completion. However, the main stage is only 50% complete. You move a few of the human resources to the main stage team. Which technique did you use?
A. Scheduling tool
B. Adjusting leads and lags
C. Resource levelling
D. Schedule compression
Answer: C, Resource leveling is a technique that is used to allot the proper amount of resources to a specific task. Since one task is nearing completion, and another task is only half done, resources could be moved from the task that all tasks can be more aligned with the schedule.
16. You are the project manager on an IT project that is performing decision analysis and resolution to identify the best possible solution. There is a 10% chance that a component you are going to upgrade will be difficult to integrate and cost $3,000 in rework and delays. There is also a 50% chance that the component will save $5,000 in time and effort that would have been used to build the component from scratch. What is the expected monetary value for these two possibilities?
A. $3,300
B. $7,500
C. $2,200
D. $8,000
Answer: C, The expected monetary value(or EMV) of the problems integrating the component is the probability(10%) times the cost ($3,000), but do not forget that since it is a risk, that number should be negative. So it's EMV is 10% * $3,000 = -$300. The savings from not having to build the component from scratch is an opportunity. It has an EMV of 50% * $5,000 = $2,500. By adding them up we get -$300 + $2,500 = $2,200.
17. Schedule is represented in different ways. You are a project manager on a construction project and want to view the scheduled activities in such a way that it is easy to view the start and end dates of each activity. Which tool is the best fit for this scenario?
A. PERT chart
B. GANTT chart
C. Precedence diagram
D. Network diagram
Answer: B, GANTT chart shows activity start and end dates as well as expected durations but do not usually show dependencies. This is also called as Bar charts.
18. What is the critical path of the project? Refer to the network diagram provided in the image above.
A. ABEGH
B. ABDFH
C. ACGH
D. ABEFH
Answer: A, Critical path is the list of activities that have zero total float.
19. Which executing processes can result in change results?
A. Conduct procurements, Acquire Project Team and Manage Stakeholder Engagement
B. Manage Communications, Manage Project Team and Perform Quality Assurance
C. Perform Quality Assurance, Direct and Manage Project Work and Develop Project Team
D. Direct and Manage Project Work, Conduct Procurements and Manage Stakeholder Engagement
Answer: D, Change requests can result from the following executing processes.
- Direct and Manage Project Work
- Conduct Procurements
- Manage Stakeholder Engagement
20. Which option describes the MAIN purpose for creating a management reserve?
A. Create a reserve for unidentified risks when the project that will occur
B. Create a reserve for unidentified risks when the project that may or may not occurs
C. Create a reserve for identified risks when the project that will occur
D. Create a reserve for identified risks when the project that may or may not occurs
Answer: B, A management reserve is used to create a reserve for unidentified events that may or may not occur during the project. Management can use their experience to determine the prudence to provide a reserve for unknown events that are uncertain to occur. This type of event is sometimes described as an unknown.